Solved

Which of the Following Statements Concerning the Critical Path in Project

Question 50

Multiple Choice

Which of the following statements concerning the critical path in project network is FALSE?


A) There is always only one critical path in a project network.
B) The critical path is the sequence of activities between a project's start and finish that takes the longest to finish.
C) Activities on the critical path have zero slack.
D) Delaying an activity on the critical path delays the entire project.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents