Which of the following statements concerning the critical path in project network is FALSE?
A) There is always only one critical path in a project network.
B) The critical path is the sequence of activities between a project's start and finish that takes the longest to finish.
C) Activities on the critical path have zero slack.
D) Delaying an activity on the critical path delays the entire project.
Correct Answer:
Verified
Q32: The earliest start time for an activity
Q33: A project has three paths.A-B-C has a
Q43: The crash cost is the additional cost
Q48: Before beginning to create a PERT/CPM network
Q51: Which one of the following statements about
Q52: In a network diagram,an "activity"
A) is the
Q54: In monitoring a project, negative slack indicates
Q66: Of the four major phases in project
Q75: The correct sequence of the four major
Q76: For controlling projects, the Cost Performance Index
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents