The difference between the earliest start (ES) and the earliest finish (EF) times for any activity in a project network is the
A) activity total slack time.
B) activity free slack time.
C) estimated duration of the activity.
D) latest finish time for the activity.
Correct Answer:
Verified
Q43: Which one of the following situations is
Q49: Standard computerized scheduling packages are rarely used
Q54: In monitoring a project, negative slack indicates
Q61: Activity slack refers to how much time
Q72: If one activity along the critical path
Q74: The earliest start time (ES) for an
Q75: The correct sequence of the four major
Q80: Total slack for an activity is calculated
Q87: In planning projects, the acronym WBS stands
Q99: Among all the paths of activities in