Assume that activity G has the following times: Early start time = 7 days
Early finish time = 13 days
Late start time = 15 days
Late finish time = 21 days
Which of the following statements is TRUE about activity G?
A) Activity G takes 14 days to complete.
B) Activity G has a slack time of 8 days.
C) Activity G is on the critical path.
D) Activity G takes 2 days to complete.
Correct Answer:
Verified
Q3: Following the project defining and organizing phase,
Q6: Project managers should be able to organize
Q7: Projects, and the application of project management,
Q13: What are the primary responsibilities of a
Q14: Projects often cut across organizational lines.
Q21: Which one of the following best describes
Q26: Figure 7.1 Q27: Figure to accompany Table 7.1 Q28: A critical path is any sequence of Q39: Figure 7.1
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents