Activity slack is defined as:
A) latest start time minus earliest start time.
B) earliest start time minus latest start time.
C) earliest finish time minus latest finish time.
D) latest finish time minus earliest start time.
Correct Answer:
Verified
Q30: Figure 7.2 Q31: The _ is the sequence of activities Q32: The earliest start time for an activity Q33: The earliest start time is never the Q34: A project has three paths. A-B-C has Q36: Assume that activity G has the following Q37: Figure to accompany Table 7.1 Q38: Figure to accompany Table 7.1 Q39: Figure 7.1 Q40: Figure to accompany Table 7.1