the Pennsylvania Appliance Company Is Installing an Assembly Line

Question 158

Multiple Choice

Table 9.17
The Pennsylvania Appliance company is installing an assembly line to produce vacuum cleaners, and you, as an operations manager, are responsible for balancing the line. The work elements to be performed are listed, along with their items and immediate predecessors.
 Work  Element  Time (sec)   Immediate  Predecessor(s)  A60B40 AC30 BD20 BE40 B F60CG70DH50 F,GI20EJ60H,I\begin{array} { | c | c | c | } \begin{array} { c } \text { Work } \\\text { Element }\end{array} & \text { Time (sec) } & \begin{array} { c } \text { Immediate } \\\text { Predecessor(s) }\end{array} \\\hline \mathrm { A } & 60 & - - \\\mathrm { B } & 40 & \mathrm {~A} \\\mathrm { C } & 30 & \mathrm {~B} \\\mathrm { D } & 20 & \mathrm {~B} \\\mathrm { E } & 40 & \mathrm {~B} \\\mathrm {~F} & 60 & \mathrm { C } \\\mathrm { G } & 70 & \mathrm { D } \\\mathrm { H } & 50 & \mathrm {~F} , \mathrm { G } \\\mathrm { I } & 20 & \mathrm { E } \\\mathrm { J } & 60 & \mathrm { H } , \mathrm { I } \\\hline\end{array}
-Use the information in Table 9.17.The company is planning to operate two shifts per day,eight hours per shift.If the desired output rate of the line is 480 units per day,what is the cycle time?


A) 60 seconds
B) 120 seconds
C) 180 seconds
D) 240 seconds

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents