Table 9.17
The Pennsylvania Appliance company is installing an assembly line to produce vacuum cleaners, and you, as an operations manager, are responsible for balancing the line. The work elements to be performed are listed, along with their items and immediate predecessors.
-Use the information in Table 9.17.The company is planning to operate two shifts per day,eight hours per shift.If the desired output rate of the line is 480 units per day,what is the cycle time?
A) 60 seconds
B) 120 seconds
C) 180 seconds
D) 240 seconds
Correct Answer:
Verified
Q101: Location factors can be divided into _
Q110: Fun Vehicles, Inc. makes beach buggies on
Q121: Good schools, recreational facilities, cultural events, and
Q153: Table 9.20
The following information is known
Q154: Table 9.21
Table 7.21 The following information
Q155: Table 9.18
A company desires to set
Q156: Given the following data about an
Q159: Table 9.18
A company desires to set
Q160: The production of a particular product
Q162: Table 9.23
The Terminal Company is attempting
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents