During the erection of concrete tilt- up wall panels, a gap is left between the bottom of a panel and the top of the footing. This gap is approximately
A) 1 in. to 2 in.
B) 2 in. to 3 in.
C) 1/2 in. to 1 in.
D) none of the above.
Correct Answer:
Verified
Q34: Reinforced- concrete tilt- up walls are generally
Q35: The most commonly used method of connecting
Q36: The most commonly used strength of concrete
Q37: What is the function of bond beams
Q38: What is the role of vertical reinforcement
Q40: In which locations are bond beams needed
Q41: The tunnel- form construction is limited in
Q42: The tilt- up wall construction uses load-
Q43: The dimensions of length and width of
Q44: Bond beams in load- bearing masonry walls