Petroleum Inc. (PI) controls off-shore oil leases. It is considering the construction of a deep-sea oil rig at a cost of $500 million. The price of oil is $100/bbl. and extraction costs are $50/bbl. PI expects costs to remain constant. The rig will produce an estimated 1,200,000 bbl. per year forever. The risk-free rate is 10 percent per year, which is also the cost of capital. (Ignore taxes) . Suppose that oil prices are uncertain and are equally likely to be $120/bbl. or $80/bbl. next year. Suppose that PI has the option to postpone the project by one year. Calculate the value of the real option to postpone the project for one year. (There is some rounding in the answer.)
A) +$30 million
B) +$50 million
C) +$54 million
D) +$70 million
Correct Answer:
Verified
Q17: You obtain the following data for year
Q18: Which of the following statements most appropriately
Q19: A project requires an initial investment in
Q20: A project requires an initial investment in
Q21: The Taj Mahal Tour Company proposes to
Q23: You are planning to produce a new
Q24: Which of the following simulation outputs is
Q25: Petroleum Inc. (PI)controls offshore oil leases. It
Q26: Petroleum Inc. (PI)controls offshore oil leases. It
Q27: Monte Carlo simulation is likely to be
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents