Question 17

Multiple Choice

A project that you are considering today is expected to provide benefits worth $168,000 in one year.If the risk-free rate of interest (rf) is 4.5%,then the value of the benefits of this project today are closest to:


A) $160,440.
B) $160,766.
C) $168,000.
D) $175,560.