A construction contractor entered into a contract to build a family room addition onto Harry's home for $25,000.In order to encourage timely performance,the agreement provided that the contractor would be penalized $2,000 as liquidated damages for each day that the project was late in getting finished.The contractor was 30 days late in finishing the project,but otherwise met the terms of the agreement.What is most likely in this situation?
A) The liquidated damages clause would not be enforced due to its being excessive.
B) The liquidated damages clause would be limited to $25,000,the amount of the contract price.
C) The liquidated damages clause would be enforced.
D) The liquidated damages clause would not be enforced because the parties made a mutual mistake about when the contract would be finished.
Correct Answer:
Verified
Q61: Pat Painter contracts to paint Harry Homeowner's
Q62: Which of the following is true about
Q63: Which of the following is not an
Q65: When a court orders specific performance,it:
A) orders
Q66: What is required in order for a
Q68: Assume that a car owner contracts with
Q69: Creative Charlie had sketched plans for an
Q90: What is the general goal of awarding
Q114: The doctrine that places a duty on
Q126: Liquidated damages clauses will generally not be
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents