Which one of the following is NOT a step in designing a PERT network?
A) determining how much time is needed to complete activities and events
B) identifying the critical path
C) identifying financial resources needed to complete activities
D) listing all activities and events that must be accomplished for the project
E) designing a PERT network that reflects activities,events,and time needed
Correct Answer:
Verified
Q80: The sales force estimation method is a
Q81: The main weakness of the Gantt chart
Q82: _ is a network of project activities
Q83: Which one of the following best describes
Q84: Which planning tool are Wal-Mart managers using
Q86: A study of failed planning showed that
Q87: Which one of the following techniques is
Q88: What are some of the main reasons
Q89: Are planning tools an effective way for
Q90: An organization's plans fail when _.
A)corporate planning
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents