Garrett is a warehouse production manager and has been assigned a complex project that might result in lengthy delays.In order to coordinate all aspects of the production process,Garrett has created a(n) _____ chart.
A) ISO
B) FMS
C) Gantt
D) PERT
Correct Answer:
Verified