FancyTrends Inc., a handbag manufacturing company, assembles handbags in an assembly line using 10 workstations. The target output for an 8 hour workday is 120 bags. The sum of the task times is 30 minutes/bag. The cycle time is 4 minutes/bag. The assembly-line efficiency is _____.
A) 65%
B) 70%
C) 75%
D) 80%
Correct Answer:
Verified
Q16: _is a technique to group tasks among
Q17: One of the disadvantages of a product
Q18: Which of the following is a limitation
Q19: In a cellular layout, the procedure of
Q20: A _ is an arrangement of physical
Q22: Which of the following types of facility
Q23: One of the advantages of a product
Q24: _is the interval between successive outputs coming
Q25: Compared to product layouts, process layouts:
A) require
Q26: In the context of assembly-line balancing, _
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents