Two projects each require a current cash expenditure of $10,000.Project A will generate cash inflows of $2,000 per year for the next twelve years.Project B is expected to return $6,000 in 1 year,$4,000 at the end of year 2,and $3,000 in 3 years.Which project should be selected if funds are unavailable to finance both and capital costs are 6%?
A) Project B because it has a shorter payback period.
B) Project B because it has a higher IRR
C) Project A because it has a higher IRR
D) Project A because it has a higher NPV
E) Project B because it has a higher NPV
Correct Answer:
Verified
Q14: You are considering the purchase of an
Q15: The primary problem with the NPV technique
Q17: Most errors committed in capital budgeting analysis
Q18: The most widely used capital budgeting technique
Q20: According to the net present value technique,a
Q21: The _ is the exact amount of
Q22: What is the NPV of the Boeing
Q23: Michigan Mattress Company is considering the purchase
Q24: All of the following are considered to
Q148: On a purely theoretical basis, the NPV
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents