Two Projects Each Require a Current Cash Expenditure of $10,000

Question 19

Multiple Choice

Two projects each require a current cash expenditure of $10,000.Project A will generate cash inflows of $2,000 per year for the next twelve years.Project B is expected to return $6,000 in 1 year,$4,000 at the end of year 2,and $3,000 in 3 years.Which project should be selected if funds are unavailable to finance both and capital costs are 6%?


A) Project B because it has a shorter payback period.
B) Project B because it has a higher IRR
C) Project A because it has a higher IRR
D) Project A because it has a higher NPV
E) Project B because it has a higher NPV

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents