Aztec Bromac budgeted the following cost standards for the current year: Direct materials = 2.8 kilos per unit @ $3.00 per kilo
Direct labour = 1.5 hours per unit @ $6 per hour
Actual production and costs were as follows:
Units produced = 3,600
Direct materials used = 9,000 kg.
Direct materials purchased = 10,000 kg. @ a cost of $29,000
Direct labour incurred = 4,000 hours at a cost of $26,000
The material price variance for materials purchased was :
A) $1,000 F
B) $1,000 U
C) $2,000 F
D) $2,000 U
Correct Answer:
Verified
Q103: The journal entry to record the
Q104: Scenesay Ltd is a capital intensive
Q105: Aztec Bromac budgeted the following cost standards
Q106: Aztec Bromac budgeted the following cost standards
Q107: Tycoon Manufacturing uses a standard costing
Q109: Scenesay Ltd is a capital intensive
Q110: Scenesay Ltd is a capital intensive
Q111: Adizero Ltd uses a standard cost
Q112: Adizero Ltd uses a standard cost
Q113: Scenesay Ltd is a capital intensive
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents