Estimated production overhead in the machining department is $200,000 and actual overhead is $204,000 and estimated machine hours in the machining department are 4,000 hours and actual machine hours are 3,700 hours. Job 12B used 20 machine hours. Using normal costing what is the machining department overhead charged to job 12B?


A) $1,081
B) $50
C) $54
D) $1,000

Correct Answer: