The Miami Group receives $240,000 a month that is delayed an average of 2 days and another $360,000 a month that is delayed an average of 3 days. What is the average daily float?
A) $43,000
B) $45,000
C) $48,000
D) $52,000
E) $54,000
Correct Answer: