A region is considering two sites on which to locate a new wastewater treatment plant. Site A has been owned by the region for five years and the region initially paid $200,000 for the land.The current market value of the site is $400,000.Site B is land the region would have to purchase for $300,000.What is the social opportunity cost of each site?
A) $200,000 for Site A; $300,000 for Site B
B) $300,000 for Site A; $300,000 for Site B
C) $400,000 for Site A; $300,000 for Site B
D) The social opportunity cost should be state for the project, not each site and would be equal to the lowest value for either site, $200,000
Correct Answer:
Verified
Q1: If the before/after principle were applied to
Q5: Social costs are equal to
A) private welfare
Q6: When evaluating proposals for building a new
Q11: Refer to the Figure above.Panel (b) represents
Q12: Refer to the Figure above.Panel (a) represents
Q13: Suppose a manufacturing firm that is about
Q15: When examining the costs associated with a
Q16: Another term for pollution taxes is _.
Q17: A city is evaluating a proposal to
Q18: Illegal roadside dumping resulting from the introduction
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents