In a production plant,800 parts per day are needed.A standard container holds 100 parts.It takes half a day to receive parts once the move card is released.A safety stock of 100 parts is usually maintained.What is the number of kanban cards needed?
A) 3
B) 4
C) 5
D) 8
Correct Answer:
Verified