Solved

The Materials Manager for a Tire Manufacturer Must Periodically Place

Question 72

Multiple Choice

The materials manager for a tire manufacturer must periodically place orders for a key chemical,one of the raw materials used in producing tires.The manager knows that manufacturing uses the chemical at a rate of 300 lbs.each week,and the lead time for delivery is 4 days.Assume that the manufacturing operation runs 5 days a week.At what point should the chemical be reordered?


A) When 0 lbs.are remaining
B) When 240 lbs.are remaining
C) When 375 lbs.are remaining
D) When 1200 lbs.are remaining

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents