Solved

Craft Construction
Craft Construction Entered into a Contract to Construct

Question 49

Essay

Craft Construction
Craft Construction entered into a contract to construct a generator station for a utility customer. The project was started in 2016 and completed in 2017. Cost and other information is presented below.
20162017 Costs incurred during the year $225,000$550,000 Estimated costs to complete 450,0000 -  Billings during the year 200,000700,000 Cash collections during the year 150,000750,000\begin{array}{lrc}&2016&2017\\\text { Costs incurred during the year } & \$ 225,000 & \$ 550,000 \\\text { Estimated costs to complete } & 450,000 & -0 \text { - } \\\text { Billings during the year } & 200,000 & 700,000 \\\text { Cash collections during the year } & 150,000 & 750,000\end{array}

-Refer to Craft Construction. Assume Craft uses the percentage-of-completion method for revenue recognition. Prepare all journal entries to record costs, billings, collections and profit recognition.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents