Craft Construction Entered into a Contract to Construct

Question 139

Essay

Craft Construction
Craft Construction entered into a contract to construct a generator station for a utility customer. The project was started in 2019 and completed in 2020. Cost and other information is presented below.
20192020 Costs incurred during the year $225,000$550,000 Estimated costs to complete 450,0000 Billings during the year 200,000700,000 Cash collections during the year 150,000750,000\begin{array} { | l | c | c | } \hline & \underline { 2019 } & \underline { 2020 } \\\hline \text { Costs incurred during the year } & \$ 225,000 & \$ 550,000 \\\hline \text { Estimated costs to complete } & 450,000 & - 0 - \\\hline \text { Billings during the year } & 200,000 & 700,000 \\\hline \text { Cash collections during the year } & 150,000 & 750,000 \\\hline\end{array}
-Craft Construction entered into a contract to construct a generator station for a utility customer. The project was started in 2019 and completed in 2020. Cost and other information is presented below.
2019 2020
Costs incurred during the year $225,000 $550,000
Estimated costs to complete 450,000 -0-
Billings during the year 200,000 700,000
Cash collections during the year 150,000 750,000
Assume Craft uses the percentage-of-completion method for revenue recognition. Prepare all journal entries to record costs, billings, collections and profit recognition.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents