In an MRP problem, A is an MPS item. Every A requires 2 B's and 3 C's. Every B requires 5 C's. All lead times are two periods. All initial inventory values are 0. Use lot-for-lot method for order quantities for all items. If gross requirement for A is 500 in period 8, what will be the planned order release for B in period 4?
A) 0
B) 1,000
C) 500
D) 1,500
E) 6,500
Correct Answer:
Verified
Q63: Which of the following is the planned-order
Q67: Which of the following is the net
Q69: Which of the following can be used
Q77: We would expect to see which of
Q81: In an MRP problem, A is an
Q82: From the list below select the one
Q83: In an MRP problem, A is an
Q84: In an MRP problem, A is an
Q86: Freezing the master schedule is:
A) not truly
Q88: Under the lot-for-lot (L4L) lot-sizing technique as
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents