You have just used the network planning model and found the critical path length is 60 days and there are two critical paths. The standard deviation of the first critical path is 10 days and the s.d. of the second critical path is 15 days. The probability that the project will be completed in 70 days or less is equal to (2 decimal accuracy)
A) 0.84
B) 0.25
C) 0.16
D) 0.75
E) 0.66
Correct Answer:
Verified
Q43: You have just been assigned to oversee
Q62: You have collected the data for a
Q63: In CPM analysis, it is generally expected
Q64: In a project analysis using three time
Q65: You have just used the network planning
Q67: You have just performed a CPM analysis
Q67: Below are the data for a Time-Cost
Q68: You have the following time and cost
Q69: Below are the data for a Time-Cost
Q70: You have just used the network planning
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents