The Manager of a Project Causes a Catastrophic Failure in the Project

Question 75

Multiple Choice

The manager of a project causes a catastrophic failure in the project that threatens the timely delivery of the project. Frank, another project manager, is asked to take over. He initiates a backup plan created by him, and he takes critical steps to recover from the setback and salvage the project. In this scenario, Frank is most likely using a(n) _____.


A) Langley histogram
B) logic chart
C) risk profile
D) FMEA chart
E) RACI matrix