The Following Information Is for Ogden Company for the Month  Utilities $44,500 Depreciation 53,500 Insurance 38,600\begin{array} { l r } \text { Utilities } & \$ 44,500 \\\text { Depreciation } & 53,500 \\\text { Insurance } & 38,600\end{array}

Question 147

Essay

The following information is for Ogden Company for the month of November:
1. Factory overhead costs are applied to jobs at the predetermined rate of $80 per labor-hour. Job X-14 incurred 2,300 labor-hours; Job SM-4 used 1,850 labor-hours.
2. Job X-14 was shipped to customers during November. Job X-14 had a gross margin of 24 percent based on manufacturing cost.
3. Job SM-4 was still in process at the end of November.
4. Factory utilities, factory depreciation, and factory insurance incurred is summarized by these factory vouchers, invoices, and cost memos:
 Utilities $44,500 Depreciation 53,500 Insurance 38,600\begin{array} { l r } \text { Utilities } & \$ 44,500 \\\text { Depreciation } & 53,500 \\\text { Insurance } & 38,600\end{array}
5. The Company purchased the following direct materials and indirect materials:
 Material A $6,000 Material B 7,000 Indirect materials 4,250 Total $17,250\begin{array} { l r } \text { Material A } & \$ 6,000 \\\text { Material B } & 7,000 \\\text { Indirect materials } & \underline{4,250 }\\\text { Total } &\underline{ \$ 17,250}\end{array}
6. Direct materials and indirect materials used are as follows:
Job X-14Job SM-4Total Material A $5,450$33,000$38,450 Material B 1,65025,50027,150 Subtotal $7,100$58,500$65,600 Indirect materials66,500 Total$132,100\begin{array}{lrrrrrr}&\text {Job X-14}&\text {Job SM-4}&\text {Total}\\\text { Material A } & \$ 5,450 & \$ 33,000 & \$ 38,450 \\\text { Material B } & 1,650 & 25,500 & 27,150 \\\text { Subtotal } & \$ 7,100 & \$ 58,500 & \$ 65,600\\\text { Indirect materials}&&&66,500\\\text { Total}&&&\$132,100\end{array}

7. Factory labor incurred for the two jobs and indirect labor is as follows:
 Job X-14 $32,200 Job SM-4 25,900 Indirect labor 122,000Total$180,000\begin{array} { l r } \text { Job X-14 } & \$ 32,200 \\\text { Job SM-4 } & 25,900 \\\text { Indirect labor } & \underline{122,000} \\\text{Total} & \underline{\$ 180,000}\\\end{array}
Required:
Calculate the total manufacturing cost for Job X-14 and Job SM-4 for November.

Correct Answer:

verifed

Verified

\[\begin{array} { l r r r }
& \text { J...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents