A gentleman farmer maniacally works on academic projects to raise funds for his true passion, farming. He has identified seven tasks and developed three time estimates (all in days) of the next big project on the farm, replacing the fence at the comedy pasture. Tasks, precedence requirements, and time estimates are shown in the table. What is the expected completion time of the project? 
A) 32 days
B) 33 days
C) 34 days
D) 35 days
Correct Answer:
Verified
Q43: Hammock activities break a task into greater
Q46: What is the early start time for
Q48: What is the early start time for
Q49: What is the early finish time for
Q52: Use the values in the table to
Q53: What are three methods of duration estimation
Q53: What is the late finish time for
Q54: What is the late start time for
Q55: A gentleman farmer maniacally works on academic
Q60: ![]()
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents