Multiple Choice
Use the information in the table to determine the late finish time for Activity B. 
A) Day 17
B) Day 20
C) Day 23
D) Day 26
Correct Answer:
Verified
Related Questions
Q58: What is the late start time for
Q59: Use the values in the table to
Q60: Use the information in the table to
Q62: A gentleman farmer maniacally works on academic
Q64: Compute early and late start and finish
Q65: What is the slack time for Activity