It was fortunate that the project budget included contingency funding;the top manager had not foreseen that the project would need the services of their elite slide rule squad in more than one area at the same time.Design couldn't complete their work without their services,nor could marketing,or production.Contingency funds came in handy to meet the unanticipated:
A) Change in project scope.
B) Abnormal project conditions.
C) Consequences of Murphy's Law.
D) Interaction costs.
Correct Answer:
Verified
Q93: "If the weather holds and the utility
Q94: A disadvantage of contingency funds is:
A)A recognition
Q95: Contingency money is:
A)The money that must be
Q96: What is activity-based costing and how is
Q97: What is the total project budget
Q99: An allocation of extra funds to cover
Q100: "If anything can go wrong it often
Q101: A budget contingency of $1 million on
Q102: What are three benefits to the use
Q103: A contingency rate of 10% on a
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents