The mouse executive board meeting was drawing to a conclusion;the only way they would be able to detect the presence of the cat was to tie a bell around its tail.Under their risk management identification scheme,this would fall under:
A) Commercial risk.
B) Execution risk.
C) Financial risk.
D) Technical risk.
Correct Answer: