The difference between the earliest start (ES) and the earliest finish (EF) times for any activity in a project network is the
A) estimated duration of the activity.
B) latest finish time for the activity.
C) activity total slack time.
D) activity free slack time.
Correct Answer:
Verified
Q19: In an activity- on- node (AON) network,
Q20: The _ is a statement of all
Q20: Which one of the following situations is
Q21: _ is the shortest time in which
Q22: What are the benefits of using CPM/PERT?
Q25: The _ is the probable time required
Q26: The probability that a project will be
Q27: _ is the smallest unit of work
Q28: The additional cost associated with reducing an
Q29: Resource allocation is an attempt to shift