Table
A company uses a kanban system. The daily demand for part is 4000 units. The average waiting time for a container of parts is day. The processing time for a container of part is day, and a container holds 300 units.
-Use the information in Table 8.3. How many kanban containers would be required if a 5 % efficiency factor is used?
A) 10 or less
B) 11 or 12
C) 13 or 14
D) 15 or more
Correct Answer:
Verified
Q6: There are many requirements for the successful
Q7: When implementing a JIT system,
A) it is
Q8: JIT systems maintain inventory in small lot
Q9: Which one of the following statements is
Q10: A kanban system is an important mechanism
Q12: A supplier to a company using JIT
Q13: When a push system is replaced by
Q14: Of the following statements, which one is
Q15: When mixed model scheduling is used on
Q16: The just- in- time (JIT) philosophy is
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents