Table 13.5.
-Use the information in Table 13.5. Which of the statements concerning item RST is TRUE? (Examine each answer independently.)
A) If the scheduled receipt in week 2 were delayed until week 3, there would be a planned order release in week 1.
B) If the gross requirements for week 8 were 100 units instead of 60 units, the projected on- hand inventory for week 8 would be 0 units.
C) If the safety stock level was 20 units instead of 0 units, there would be a planned order release in week 2.
D) If the safety stock level were 30 units instead of 0 units, the planned receipt in week 7 would be 110 units.
Correct Answer:
Verified
Q8: Which of the following statements about MRP
Q9: Use the following MRP record to answer
Q10: Use the following MRP record to answer
Q11: The purpose of Finite Capacity Scheduling is
Q12: Use the following MRP record to answer
Q14: Which one of the following is an
Q15: Table 13.7. Q16: A technique for projecting time- phased requirements Q17: Which of the following statements about MRP Q18: Table 13.7![]()
![]()
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents