Table 13.3
Consider the following MPS, BOM, and inventory data. You will need a blank MRP record to answer the question(s) .
Master Production Schedule: the following table shows the MPS start quantities.
Week
Bill of Material
-End item A uses 1 each of component C and 1 each of subassembly D.
-Subassembly D uses 2 each of component E and 2 each of component F.
-End item B uses 1 each of component C and 2 each of component F.
Selected Inventory Data
Item
-Use the information in Table 13.3. Which one of the following statements about item F is TRUE?
A) Its first planned receipt is for 215 units in week 4.
B) There will be exactly one action notice, which calls for the release of a new order.
C) There will be exactly one action notice, which calls for the delay of the scheduled receipt until week 2.
D) The first planned order release is for 205 units in week 3.
Correct Answer:
Verified
Q21: Which one of the following statements concerning
Q22: Table 13.1 Q23: Table 13.3 Q24: Table 13.5. Q25: Table 13.8 Q27: Table 13.7 Q28: Use the following MRP record to Q29: Which one of the following statements about Q30: Table 13.2. Q31: Which one of the following systems is Unlock this Answer For Free Now! View this answer and more for free by performing one of the following actions Scan the QR code to install the App and get 2 free unlocks Unlock quizzes for free by uploading documents
Consider the following MPS, BOM,
Sunshine Manufacture produces three products, X,