Which of the Following Statements Regarding the Output from MRP

Question 51

Multiple Choice

Which of the following statements regarding the output from MRP systems is FALSE?


A) A materials requirement plan is generated for each component item.
B) Action notices are generated to make decisions about releasing new orders and adjusting the due dates of scheduled receipts.
C) Priority reports such as dispatch lists and supplier schedules are generated.
D) Typically the capacity limitations of processing equipment are explicitly recognized by MRP systems when planned orders are calculated.

Correct Answer:

verifed

Verified