Solved

Table 13.8 Sunshine Manufacture Produces Three Products, X, Y, and Z. the Z

Question 68

Multiple Choice

Table 13.8
Sunshine Manufacture produces three products, X, Y, and Z. The production of these end items is controlled by an MRP
system. Each end item X is assembled with two components of A and one component of B. Each end item of Y is assembled
with two components of C and one component of A, each component of C is manufactured from one unit of B. End item Z is
assembled from one unit of D and one unit of C, D is manufactured from one unit of A, and C is manufactured from one unit
of B.
-Use the information in Table 13.8. If item C has a manufacturing lead time of two weeks and a planned receipt of 65 units is needed in week 4, which of the following statements is TRUE?


A) The planned order release in week 2 for item C is 130 units.
B) The gross requirements for item B in week 2 is 65 units.
C) The gross requirements for item B in week 2 is 130 units.
D) The gross requirements for item B in week 4 are at least 65 units.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents