Table 124
a Company Is Attempting to Schedule Workers for the the Next

Question 29

Multiple Choice

Table 12.4
A company is attempting to schedule workers for the next seven days. The daily requirements, in number of workers needed,
are shown below.
 Day MTWTHFSSU Requirement 5484623\begin{array} { | r | c | c | c | c | c | c | c | } \hline \text { Day } & \mathrm { M } & \mathrm { T } & \mathrm { W } & \mathrm { TH } & \mathrm { F } & \mathrm { S } & \mathrm { SU } \\\hline \text { Requirement } & 5 & 4 & 8 & 4 & 6 & 2 & 3 \\\hline\end{array}
Each worker must work five days per week and must have two consecutive days off.
-Use the information in Table 12.4. How much total slack will be generated from the schedule?


A) less than 7 days
B) 7 days
C) 8 days
D) more than 8 days

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents