A line balancing solution has been developed for the assembly line for fertilizer spreaders at Green Grass, Inc. The desired output rate of 30 spreaders per hour will be achieved. The sum of times for all tasks performed on the line is 1200 seconds for each spreader assembled. This is the total productive time. Which of the following statements must be TRUE?
A) If the solution calls for 11 stations, the efficiency is 80%.
B) The "theoretical minimum" number of stations is 10.
C) If solution calls for 12 stations, the efficiency is 80%.
D) The cycle time is 30 seconds per spreader.
Correct Answer:
Verified
Q22: Which of the following group of location
Q23: Which of the following is an advantage
Q24: Table 10.15
Balance the following line for
Q25: Table 10.9
The administration department of a
Q26: Which one of the following statements about
Q28: Kiddie Clothes wishes to locate its
Q29: Which one of the following statements about
Q30: Table 10.23
The Terminal Company is attempting
Q31: Table 10.1
A single facility is needed
Q32: Table 10.12
A company with a process
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents