Table 10.17
The Pennsylvania Appliance company is installing an assembly line to produce vacuum cleaners, and you, as an operations
manager, are responsible for balancing the line. The work elements to be performed are listed, along with their items and
immediate predecessors.
-Use the information in Table 10.17. What is the theoretical minimum number of stations (TM) for the line? If you are using the longest work- element time rule, how many workstations do you need?
A) TM = 3; solution = 3 stations
B) TM = 3; solution = 4 stations
C) TM = 4; solution = 4 stations
D) TM = 4; solution = 5 stations
Correct Answer:
Verified
Q52: The group of location factors found to
Q53: Table 10.8
The Neale Company has four
Q54: Which one of the following statements is
Q55: A grower and shipper of fresh
Q58: Table 10.20
The following information is known
Q59: The Euclidean distance between points A (15,
Q60: Which one of the following statements is
Q61: Which one is a possible disadvantage of
Q62: Excel Products is planning a new
Q110: Fun Vehicles, Inc. makes beach buggies on
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents