Table 1017
the Pennsylvania Appliance Company Is Installing an Assembly Line

Question 74

Multiple Choice

Table 10.17
The Pennsylvania Appliance company is installing an assembly line to produce vacuum cleaners, and you, as an operations manager, are responsible for balancing the line. The work elements to be performed are listed, along with their items and immediate predecessors.
 Work  Element  Time (sec)   Immediate  Predecessor(s)   A 60 B 40 A  C 30 B  D 20 B  E 40 B  F 60 C  G 70 D  H 50 F, G  I 20 E  J 60 H, I \begin{array} { | c | c | c | } \hline \begin{array} { c } \text { Work } \\\text { Element }\end{array} & \text { Time (sec) } & \begin{array} { c } \text { Immediate } \\\text { Predecessor(s) }\end{array} \\\hline \text { A } & 60 & - - \\\text { B } & 40 & \text { A } \\\text { C } & 30 & \text { B } \\\text { D } & 20 & \text { B } \\\text { E } & 40 & \text { B } \\\text { F } & 60 & \text { C } \\\text { G } & 70 & \text { D } \\\text { H } & 50 & \text { F, G } \\\text { I } & 20 & \text { E } \\\text { J } & 60 & \text { H, I } \\\hline\end{array}
-Use the information in Table 10.17. What is the efficiency of the longest work- element time solution just found?


A) less than 91%
B) more than 91% and less than 93%
C) more than 93% and less than 95%
D) more than 95%

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents