Solved

A Project Costs $2

Question 110

Multiple Choice

A project costs $2.43 million and has no salvage value.Depreciation is straight-line to zero over the five-year life of the project.Sales are projected at 64,000 units per year, price per unit is $73.29, variable cost per unit is $42.93, and fixed costs are $623,000 per year.The tax rate is 35 percent, and the required rate of return is 11percent.What is the sensitivity of NPV to a 100-unit increase in the sales figure?


A) $9,198.40
B) $8,609.18
C) $8,097.40
D) $7,293.48
E) $7,557.12

Correct Answer:

verifed

Verified

Unlock this answer now