Definitive estimates can vary by as much as:
A) +10% to - 5%.
B) +75% to - 25%.
C) +25% to - 10%.
D) +10% to - 10%.
Correct Answer:
Verified
Q13: A WBS dictionary:
A)is part of the project
Q14: Using a bottom- up approach for creating
Q15: _dependencies indicate the relationship of activities that
Q16: Network_ are templates developed from previous projects
Q17: _is the time delay between completion of
Q19: The need to delay activities requiring more
Q20: The process of subdividing tasks to make
Q21: Another term for a product breakdown structure
Q22: All of the following are estimation phases
Q23: When determining the sequence of activities, the