Which of the following is not a fundamental, inherent weakness in the probabilistic approach to PERT?
A) One may have difficulty in obtaining three reliable time estimates for each activity.
B) There is the possibility of large variances for non-critical activities.
C) The assumption that activity times are independent of each other.
D) The assumption that possible overall project completion times are Beta-distributed.
Correct Answer:
Verified
Q28: Discuss the assumptions required for determining the
Q29: In the PERT probabilistic approach, statisticians have
Q30: Activity C is an immediate predecessor of
Q31: Ajax is about to embark on
Q32: A project contains activities D and K.Activity
Q34: PERT/Cost is a cost-center based system, where
Q35: PERT/Cost:
A)allows for activity interruption.
B)assumes costs are evenly
Q36: Let B = budgeted total cost for
Q37: Which of the following is false?
A)Crashing an
Q38: In using PERT/CPM, why does management need
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents