Let Ti = normal completion time for task iRi = crash completion time for task i Ci = normal cost for task i
Hi = crash cost for task i
Xi = start time for task i
Yi = amount of time by which task i is to be crashed.
What is the objective function of a linear programming model for project crashing?
A) all i Yi(Hi - Ci) /(Ti - Ri)
B) all i on critical path Yi(Hi - Ci) /(Ti - Ri)
C) all i XiYi
D) all i YiHi
Correct Answer:
Verified
Q19: Using the Critical Path Method, the normal
Q20: A disadvantage of Gantt chart methodology is
Q21: When attempting to use PERT methodology, how
Q22: In the critical path method (CPM), crashing
Q23: Activity T has a single immediate predecessor,
Q25: A "forward pass" in network analysis of
Q26: Which of the following is true?
A)PERT gives
Q27: The probabilistic approach characterized by PERT does
Q28: Discuss the assumptions required for determining the
Q29: In the PERT probabilistic approach, statisticians have
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents