Given the Following Data for Work Packages in a PERT/Cost

Question 41

Essay

Given the following data for work packages in a PERT/Cost network at week 18:
 Activity  Immediate  Predecessors  Budgeted  Time  (weeks)  Budgeted  Value  Percent  Complete  Expense To  Date  A 12$50,0001008$48,000 B 8$20,0001008$21,000 C  A 6$60,000758$40,000 D  B 16$40,000508$25,000 E  C, D 16$45,000080 F  B 28$80,000758$55,000\begin{array}{cccccc}\text { Activity } & \begin{array}{c}\text { Immediate } \\\text { Predecessors }\end{array} & \begin{array}{c}\text { Budgeted } \\\text { Time } \\\text { (weeks) }\end{array} & \begin{array}{c}\text { Budgeted } \\\text { Value }\end{array} & \begin{array}{c}\text { Percent } \\\text { Complete }\end{array} & \begin{array}{c}\text { Expense To } \\\text { Date }\end{array} \\\text { A } & -- & 12 & \$ 50,000 & 1008 & \$ 48,000 \\\text { B } & -- & 8 & \$ 20,000 & 1008 & \$ 21,000 \\\text { C } & \text { A } & 6 & \$ 60,000 & 758 & \$ 40,000 \\\text { D } & \text { B } & 16 & \$ 40,000 & 508 & \$ 25,000 \\\text { E } & \text { C, D } & 16 & \$ 45,000 & 08 & 0 \\\text { F } & \text { B } & 28 & \$ 80,000 & 758 & \$ 55,000\end{array}
A.Is the project currently experiencing a cost overrun?
B.Is the project on target to be completed within 40 weeks?
C.What corrective action, if any, could you recommend?

Correct Answer:

verifed

Verified


A.(No.Value of work to date = $195,000....

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents