Projects with a Negative Net Present Value Will Always Have

Question 50

Multiple Choice

Projects with a negative net present value will always have a(n)


A) payback period longer than the useful life of the investment.
B) internal rate of return that is less than the required rate of return.
C) accounting rate of return that is negative.
D) series of cash outflows that is greater than the initial cost of the project.

Correct Answer: