Use the Table for the Question(s) Below -Assuming That Your Capital Is Constrained, Which Project Should You

Question 21

Multiple Choice

Use the table for the question(s) below.
Consider the following list of projects:
 Project  Investment  NPV  A 135,0006,000 B 200,00030,000C125,00020,000D150,0002,000E175,00010,000F75,00010,000G80,0009,000H200,00020,000I50,0004,000\begin{array} { l r r } \hline \text { Project } & \text { Investment } & \text { NPV } \\\hline \text { A } & 135,000 & 6,000 \\\hline \text { B } & 200,000 & 30,000 \\\hline \mathrm { C } & 125,000 & 20,000 \\\hline \mathrm { D } & 150,000 & 2,000 \\\hline \mathrm { E } & 175,000 & 10,000 \\\hline \mathrm { F } & 75,000 & 10,000 \\\hline \mathrm { G } & 80,000 & 9,000 \\\hline \mathrm { H } & 200,000 & 20,000 \\\hline \mathrm { I } & 50,000 & 4,000 \\\hline\end{array}
-Assuming that your capital is constrained, which project should you invest in first?


A) Project F
B) Project C
C) Project B
D) Project G

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents