Pont Bridges Corp

Question 34

Multiple Choice

Pont Bridges Corp.had signed a contract to build a new bridge for $5,000,000.Initially their estimated total costs were $4,400,000.During the first year, they realized their costs were going to be greater than originally estimated.They now expect total costs to be $5,500,000, but they cannot change the contract price.If Pont uses the percentage-of-completion method to recognize revenue, how much gross profit (loss) related to the project should they recognize in the first year?


A) ($500,000)
B) ($400,000)
C) $0
D) $480,000