Solved

Consider the Table Below with Information Regarding Each Activity, Immediate

Question 46

Essay

Consider the table below with information regarding each activity, immediate predecessors, and duration estimates (in minutes) for each activity.  Activity  Immediate  Predecessors  Minimum  Time  Likely Time  Maximum  Time  A 679 B 4911 C  A 3912 D  B 2612 E  B, C 3510 F  D 479 G  E 4715\begin{array} { c | c | c | c | c } \hline \text { Activity } & \begin{array} { c } \text { Immediate } \\\text { Predecessors }\end{array} & \begin{array} { c } \text { Minimum } \\\text { Time }\end{array} & \text { Likely Time } & \begin{array} { c } \text { Maximum } \\\text { Time }\end{array} \\\hline \text { A } & - & 6 & 7 & 9 \\\text { B } & - & 4 & 9 & 11 \\\text { C } & \text { A } & 3 & 9 & 12 \\\text { D } & \text { B } & 2 & 6 & 12 \\\text { E } & \text { B, C } & 3 & 5 & 10 \\\text { F } & \text { D } & 4 & 7 & 9 \\\text { G } & \text { E } & 4 & 7 & 15\end{array}  Consider the table below with information regarding each activity, immediate predecessors, and duration estimates (in minutes) for each activity.  \begin{array} { c | c | c | c | c }  \hline \text { Activity } & \begin{array} { c }  \text { Immediate } \\ \text { Predecessors } \end{array} & \begin{array} { c }  \text { Minimum } \\ \text { Time } \end{array} & \text { Likely Time } & \begin{array} { c }  \text { Maximum } \\ \text { Time } \end{array} \\ \hline \text { A } & - & 6 & 7 & 9 \\ \text { B } & - & 4 & 9 & 11 \\ \text { C } & \text { A } & 3 & 9 & 12 \\ \text { D } & \text { B } & 2 & 6 & 12 \\ \text { E } & \text { B, C } & 3 & 5 & 10 \\ \text { F } & \text { D } & 4 & 7 & 9 \\ \text { G } & \text { E } & 4 & 7 & 15 \end{array}     a. Using the PERT distribution in ASP to represent the duration of each activity, construct a simulation model to compute the total time to complete the task. b. What is the expected duration of the entire project? What is the standard deviation of the project duration? c. What is the likelihood that the project will be complete in 26 minutes?
a. Using the PERT distribution in ASP to represent the duration of each activity, construct a simulation model to compute the total time to complete the task.
b. What is the expected duration of the entire project? What is the standard deviation of the project duration?
c. What is the likelihood that the project will be complete in 26 minutes?

Correct Answer:

verifed

Verified

a. Refer to the screenshot below for the...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents