The following information relates to Lancashire Manufacturing: To produce a unit of product: There is a wait time of 8 minutes before the mixing department begins a batch, 5 minutes between the mixing and molding departments, a move and pre-wait between molding and casting of 10 minutes, and a move and pre-wait between the casting and finishing departments of 12 minutes.
What is the production rate?
A) 8.6 units per hour
B) 7 units per hour
C) 21 units per hour
D) 19 units per hour
Correct Answer:
Verified
Q48: The worth of one or more features
Q49: The order fulfillment value stream focuses on
A)developing
Q50: In a demand-pull system
A)production is triggered by
Q51: The methodologies and concepts adopted by just-in-time
Q52: The following information relates to Lancashire
Q54: Identification of a "value stream," pursuit of
Q55: The value stream
A)is made up of all
Q56: In cellular manufacturing, cells are dedicated to:
A)produce
Q57: Which of the following is true of
Q58: The processing department can produce one unit
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents