The volume variance is caused by:
A) the difference between the activity allowed for the actual output and the budgeted activity used in computing the fixed overhead rate.
B) the difference between total budgeted fixed overhead and total standard fixed overhead assigned to production.
C) the difference between the activity allowed for the actual output and the total standard fixed overhead assigned to production.
D) the difference between the standard fixed overhead rate and the actual fixed overhead rate.
Correct Answer:
Verified
Q65: Franklin Company expected sales were 2,000 units
Q66: A sales volume variance will be favourable
Q67: Taylor Company's budgeted sales were 10,000 units
Q68: Figure 17-7
Orient Company has developed the
Q69: Figure 17-7
Orient Company has developed the
Q71: The following standard costs were developed
Q72: Figure 17-7
Orient Company has developed the
Q73: The following standard costs were developed
Q74: Figure 17-8
The following information was extracted
Q75: Figure 17-7
Orient Company has developed the
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents